Key Takeaways
- The ADU construction process runs in a set order: lot check, design, plan check and clearances, permit, staged inspections, then the Certificate of Occupancy.
- Your lot's hazard zones, your garage's permit history and your utility capacity shape the engineering more than the floor plan does.
- The city building department and the utilities set the pace, so plan around their reviews, not a single advertised timeline.
The ADU construction process in Los Angeles follows a fixed order. You confirm what your lot allows, then design and engineer the unit. The plans go through plan check, and other departments give their clearances. Once the permit is issued, you build, and the city inspects each stage. After the final inspection passes, you receive the Certificate of Occupancy. Most problems come from rushing one of those steps, especially the early ones. Below, we walk through each stage, including the utility steps and garage questions that catch homeowners off guard.
What are the steps of the ADU construction process in Los Angeles?
An ADU moves from feasibility to design, then plan check, department clearances and permit issuance. After that comes construction with inspections at each stage, and finally the Certificate of Occupancy. Some steps overlap, but none can be skipped.
Here’s the order most Los Angeles ADUs follow:
- Feasibility. Look up the lot’s zoning and hazard areas, and check the existing house, sewer line and electrical service.
- Design and engineering. A designer draws the plans, an engineer sizes the structure, and a soils report is added when the site needs one.
- Plan check. The building department reviews the plans and sends back corrections.
- Clearances. Other departments sign off on their part, such as planning, fire, sewer or utilities.
- Permit issued. Construction can start.
- Construction and inspections. The inspector checks the work at set stages before it gets covered.
- Final and release. After the final passes, the city releases power to the utility and issues the Certificate of Occupancy.
A Certificate of Occupancy is the city’s official document saying people may live in the unit. Without it, you can’t legally rent the ADU. LADBS lays out this sequence in its handout on converting an existing detached structure to an ADU, including clearances approved before the permit and certificate.
If you’re still at the starting line, our guide on how to start an ADU project the right way covers the early decisions. The city building department controls how long each review takes, so plan financing and move-in dates around its pace.
How do I check what my lot allows before paying for plans?
Look up your address on the city's zoning map before you pay for drawings. The map shows your zoning plus overlays such as hillside areas, fire hazard zones and earthquake hazard zones. Those overlays change what you can build and how it has to be engineered.
Inside the City of Los Angeles, the free tool is ZIMAS, the city’s zoning and parcel map. Check the zone, any hillside designation, a Very High Fire Hazard Severity Zone, and liquefaction or landslide areas. Liquefaction means loose, wet soil can act like liquid in a strong earthquake, which matters a lot for footings. If your street floods, check the federal flood maps too.
Each flag changes the engineering. In a fire zone, the roof, vents, siding and windows must resist embers. A hillside or liquefaction flag usually means a soils or geology report and sometimes deeper footings. On many older Los Angeles lots, the real limit is an easement, an overhead power line or a sewer line running right where the owner pictured the ADU.
Don’t assume one setback rule fits every lot; overlays can change the numbers, so confirm with City Planning. HCD’s ADU Handbook and its Addendum on changes effective January 1, 2026, explain what cities must allow. Outside the City of Los Angeles, a different building department reviews your project with its own steps.
Should I use a pre-approved standard plan or a custom design?
A pre-approved standard plan can simplify review when your lot fits the design as drawn. A custom design usually makes more sense for a sloped or narrow lot, a hazard zone, or the conversion of an existing structure.
LADBS runs a Standard Plan Program for ADUs. A design that gets built repeatedly is reviewed once, so later projects using it follow a simpler permit path. The building has been checked. Your site has not.
You still need a site plan showing where the unit sits, how utilities reach it, and how it meets setbacks and fire separation. The foundation may need changes if your soil or slope differs from what the plan assumed. Clearances from other departments still apply.
A standard plan rarely fits a garage conversion, because the walls, slab and roof already exist. It also struggles where a sewer connection, power drop or mature tree pins the unit into an odd spot. Pick the path that matches the ground you’re building on, because that choice shapes the rest of the ADU construction process.
What goes into plan check, and which clearances can hold up the permit?
Plan check needs a complete set of plans: architectural drawings, structural plans and calculations, an energy compliance report, and a soils report when the site requires one. During review, the city lists clearances from other departments, and each must be signed off before the permit is issued.
A typical ADU submittal includes:
- A site plan with property lines, setbacks, easements and utility routes
- Floor plans, elevations and sections
- Structural plans and calculations from an engineer
- An energy compliance report showing the unit meets the state energy code
- A soils or geology report when the lot’s hazards call for one
Clearances are sign-offs from departments other than building and safety. Depending on your lot, Planning, the Fire Department, Sanitation, LADWP or the Bureau of Engineering may weigh in. Each works at its own speed, and one slow sign-off can hold up finished plans. Our article on the ADU permit timeline explains how those reviews stack up.
Some work needs its own permit. Retaining walls, grading, block walls and fire sprinklers are often permitted separately. Work in the street, like a driveway apron, a sewer tie-in or anything near a street tree, needs its own approvals. When corrections come back, answer every item completely, because partial answers usually mean another round.
Is my garage conversion treated as an alteration or as new construction?
A garage with a permit on record is usually handled as an alteration, though a damaged or worn foundation or slab still has to be repaired or upgraded. A garage with no permit on record can be treated like new construction, so the foundation and framing must be checked against today's code.
Start by pulling the property’s permit history. If the garage was built without a permit, expect the building department to treat it as brand new. The foundation and the framing that carries weight and resists earthquake and wind forces will be checked and upgraded where needed. Los Angeles County’s ADU guidelines spell out this same approach.
Older Los Angeles garages share common weak spots: a thin slab with little footing under the walls, no moisture barrier, and a wide door opening with almost no bracing. Shear walls are walls sheathed and nailed to resist sideways shaking, and many garages have none. Typical fixes include new footings, steel hold-downs, new shear walls and a moisture barrier.
Old garages also hide lead paint, and some siding, flooring or roofing contains asbestos. Federal lead-safe rules, the regional air district’s asbestos notice rules and state worker safety rules apply before demolition, so test first. Our post on whether a garage can become an ADU in Los Angeles goes deeper.

Which inspections happen during the ADU construction process, and in what order?
Inspections follow the build from the ground up, starting with the foundation and ending with a final. Along the way, the inspector checks framing, rough plumbing, electrical and mechanical, insulation and drywall. Each stage has to pass before the work it covers gets hidden.
The usual order looks like this:
- Foundation, before concrete goes in: trenches, rebar and hold-down bolts.
- Underground plumbing, before the trench is backfilled.
- Framing, once walls, roof, shear walls and hardware are in place.
- Rough plumbing, electrical and mechanical, while walls are open.
- Insulation, right before the walls close.
- Drywall nailing, where the plans call for it.
- Final, including smoke and carbon monoxide alarms, fixtures and outside work.
The owner or contractor requests each inspection, and the inspector signs the job card on site, so keep it posted where it won’t get lost. Fire sprinklers, if required, get their own inspections.
A failed inspection costs time, not the project. Common misses are simple: a misplaced hold-down, missing shear wall nailing, or a pipe that doesn’t match the plans. The inspector goes by the approved plans, so discuss any field change before it’s built. That habit keeps the ADU construction process moving.
How do the ADU's electric service and the LADWP meter spot work?
Many ADUs need more power, which can mean a panel upgrade or a new service. In LADWP territory, you request a free meter spot before installing a new service panel. LADWP energizes the new service only after LADBS gives its final release.
Start with a load calculation, a simple tally of how much power the house and ADU will draw together. Electric cooking, heat pumps, water heaters and car chargers add up fast, and many older Los Angeles houses run on a small service that can’t carry a second dwelling.
Before a new residential panel goes in, request a meter spot from LADWP, a free service that sets where the meter goes. The LADBS inspector may ask to see that document before approving the panel, so request it early. LADWP turns on power only after LADBS sends the final release.
Can the ADU have its own meter or address? Sometimes. LADWP’s service rules show several metering layouts, and the right one depends on the site. Sewer, water and gas need their own planning too, and slope often decides the sewer route. Our guide to ADU sewer and electrical needs covers those choices.
Who calls DigAlert before the footings and utility trenches are dug?
Whoever does the digging, usually your contractor, contacts DigAlert at least two working days before digging, not counting the day of the call. Utilities mark only the lines they own, usually up to the meter. Private lines running out to a backyard ADU won't be marked.
DigAlert, the 811 service for Southern California, is free, and state law requires it before digging. Each utility then marks its buried lines with paint or flags.
Here’s the gap that surprises people: those marks stop at the meter. The gas line to the house, the power feed to an old garage and the backyard sewer line belong to you, and nobody marks them. Older Los Angeles lots also hide abandoned lines and shallow clay sewer pipe.
Before trenching to a detached ADU, a careful contractor will:
- Submit the DigAlert request and wait for every utility to respond.
- Trace private lines from the meters, using a private locator when needed.
- Hand dig near any marked or suspected line.
- Route the trench to avoid crossing old lines.
Hitting a gas line is dangerous and stops the job. Two days of locating is a small price.

When should you call a licensed contractor about your ADU?
Call before you buy plans, not after, especially if your garage has no permit on record, ZIMAS shows a hillside, fire or liquefaction flag, or your electrical service or sewer line seems undersized. Those conditions shape the foundation, framing and utility work, and they’re easiest to handle on paper.
Check licenses first on the Contractors State License Board website, and check engineers through the state engineering licensing board. A licensed and insured contractor like Villa Bella Construction looks at the real conditions on your lot, then recommends targeted work aimed at meeting city requirements without tearing out more than needed. The city still decides approvals and timing. Learn more on our ADUs and garage conversions page.
“The work was very well done and exceeded all my expectations.” — Cindy W., Yelp review
Villa Bella Construction is a licensed and insured general contractor, building in Los Angeles for 25 years. CSLB License #1093648 (B – General Building).
Call +1 (323) 825-9798 or send us your project details.
Learn more: ADUs and garage conversions.
Planning a construction or remodeling project in Los Angeles?
Schedule a Free On-Site Consultation or call +1 (323) 825-9798.