Key Takeaways
- State law gives the city 15 business days to say whether an ADU application is complete, then 60 days to approve or deny it. That clock only runs once the package is complete.
- A denial with a written correction list is normal. Resubmitting can restart the clock, so a complete, coordinated plan set saves the most time.
- Utility service, fire-zone, coastal, and historic reviews, along with construction inspections, run on their own schedules. The building department decides approvals and timing.
The ADU permit timeline in Los Angeles has two parts. State law sets a short window, and a longer stretch depends on your plans, your lot, and how busy the city is. The city has 15 business days to decide whether your application is complete, then 60 days to approve or deny a complete one. Even so, nobody can promise the whole process wraps up in 60 days. LADBS doesn’t publish an average ADU plan-check time, so any website quoting an exact number of days is guessing. Here’s what really sets the pace, and which parts you can control.
How long is the ADU permit timeline in Los Angeles, start to finish?
Plan on several months from first drawings to a permit in hand, and longer if your lot has hillside, fire-zone, coastal, or historic issues. Only two pieces of that time are set by state law. The rest depends on how complete your plans are and how busy the building department is.
It helps to break the timeline into phases, because each one moves at its own speed:
- Preparing to submit: survey, zoning check, design, engineering, and energy paperwork.
- Completeness check: the city has 15 business days to tell you in writing whether the application is complete.
- Plan check: the city’s review of your drawings against the building, zoning, and energy rules. For a complete application, it must end in an approval or a denial within 60 days.
- Corrections and resubmittals, if the plans come back with comments.
- Clearances from other agencies, such as utilities, sewer, or fire review.
- Permit issuance, followed by construction inspections and the final sign-off.
You control the first phase more than any other, and it’s often the longest. The middle phases run on the city’s calendar. LADBS covers only the City of Los Angeles. If your home sits in another city or in unincorporated county land, that agency runs its own process with its own workload, although the same state deadlines apply.
Keep the permit and the build separate in your head. A permit in hand doesn’t mean a finished unit. Construction and inspections come after, and the building department decides when each inspection passes. For the full build sequence, see our guide to the ADU construction process in Los Angeles.
When does the 60-day clock actually start?
The 60-day clock starts when the city has a complete application, not the day you first upload plans. If the city doesn't tell you in writing within 15 business days whether the application is complete, state law treats it as complete.
“Complete” means the city has everything it needs to review the project: drawings, required forms, calculations, and any reports your lot requires. It doesn’t mean the plans are perfect. A complete application can still get correction comments.
The California Department of Housing and Community Development lays out these deadlines in its ADU Handbook, which explains the 15-business-day completeness check and the deemed-complete rule. The 60-day decision window applies when a home already exists on the lot. If you apply for a new main house and an ADU together, the city can hold the ADU until the main house is approved.
Most of the lost time we see in an ADU permit timeline happens before the clock even starts. A missing soils report, a site plan that doesn’t match the survey, or an unsigned form can send the package back as incomplete. You can’t speed up the city, but you can make sure the clock starts on the first try.
What happens if my ADU plans are denied or the city misses a deadline?
A denial inside the 60 days usually means "fix these items," not "no ADU." The city has to give you a full written list of what's wrong and how to fix it. Once you resubmit, the review period can start over.
Homeowners often panic when they see the word denied. In practice, it works like a correction list. Each comment points to something the reviewer needs changed or explained, such as a setback dimension, a missing structural detail, energy forms that don’t match the drawings, or an undersized egress window. An egress window is a bedroom window big enough, and low enough, for a person to climb out during a fire.
HCD’s guidance to cities says a denial must include that full written list of problems and how to correct them. If a comment is vague, your designer or engineer can ask the plan checker what they need. A clear question usually gets a clear answer, and it beats guessing and getting a second round of corrections.
If the city misses its deadlines, state ADU law treats the application as complete after 15 business days, and as approved if no action is taken within 60 days. Don’t start building on that alone. Talk with the department and your design team first, because you still need an issued permit and city inspections to finish legally.
What do I need ready before I submit my ADU plans?
You need a plan set that answers the reviewer's questions before they ask them. That means a site plan based on accurate measurements, architectural and structural drawings, and Title 24 energy calculations. Hillside lots, older garages, and lots in coastal, fire, or historic zones need extra reports or reviews.
Title 24 energy calculations are the state forms that show the new unit meets California’s energy rules for insulation, windows, lighting, and heating. They’re one of several pieces that have to agree with each other. Here’s the order that works best:
- Check your lot on ZIMAS, the city’s online zoning map. It shows your zone and any hillside, fire, coastal, or historic overlays.
- Get a survey or accurate site measurements, so setbacks and the ADU footprint are drawn correctly.
- Order a soils or geology report if the lot slopes or the city’s maps flag it. A soils report tells the engineer how strong the ground is and what kind of footing it needs.
- Get structural drawings and calculations from a licensed engineer when the design isn’t a simple standard layout or when you’re reusing an existing structure.
- Prepare the Title 24 energy calculations and the green-building forms.
- Confirm the sewer and electrical paths: where the sewer line ties in, and whether the existing electrical service can carry the new unit.
- Submit the full package through ePlanLA, the online filing system LADBS explains on its Start Your Project page.
In older Los Angeles neighborhoods, the main house often has a small electrical service, and the sewer line may be old clay pipe in unknown condition. It’s better to learn that before you submit than to find it on a correction sheet. Our post on ADU sewer and electrical needs walks through both.

Is a garage conversion faster to permit than a new detached ADU?
Sometimes. A legally built garage can be converted without new setbacks and without a public hearing. Old garages often need foundation, framing, fire-separation, or energy upgrades, though, and those bring plan check comments.
The appeal is real. The walls and roof are already there, and if the garage was built with permits, the city accepts its existing location. That removes a whole category of zoning questions from your ADU permit timeline.
The catch is what’s inside the walls. Many older Los Angeles garages sit on a thin slab with no real footing. They often have no anchor bolts, and the wood near the ground has been wet for decades. An anchor bolt is a steel bolt that keeps the wall from sliding off the foundation in an earthquake. Turning that garage into living space can mean new footings, new framing, insulation, and fire separation if the garage is close to the house or the property line. Fire separation means fire-rated walls or ceilings that slow a fire from spreading between buildings.
If the garage, or an addition to it, was built without permits, expect more questions. LADBS publishes guidance on legalizing unpermitted units, and there are exceptions, especially for health and safety problems. Our page on garage conversion permit requirements in LA covers this in more detail. Our ADU and garage conversion service page explains how we check the existing structure first.
Should I use an LADBS pre-approved standard plan to speed things up?
A standard plan can shorten plan check because LADBS has already reviewed the building design itself. It only helps if the plan fits your lot, and the city still checks zoning and foundation conditions for your property.
A standard plan is an ADU design that LADBS has already reviewed against the building, residential, green building, and energy codes. You pick a plan, and the city’s review focuses on how it sits on your property. LADBS also offers a city-owned plan that owners can use for free.
The program is narrower than some ads suggest. The city’s Approved Standard Plans page warns that pre-approved plans may not be approved for some sites or site conditions, and some plans on its list are marked expired. Standard plans tend to fall short on sloped lots, tight side yards, oddly shaped lots, poor soil, and lots in special zones.
Before you commit, confirm three things: the plan is current, its footprint fits within your setbacks, and its foundation design suits your soil. If any of those don’t line up, a design drawn for your lot may move just as fast, with fewer surprises at the counter.
Which other approvals and utility steps can add time?
Utility service, sewer or driveway work in the street, fire-zone review, coastal permits, and historic-district review each run on their own schedule. The 60-day state deadline covers the city's ADU decision. It doesn't cover the utility or these other reviews.
Electrical is the one that surprises people. Before you install a new service panel for an ADU, you request a free meter spot from LADWP, which marks where the meter will go. According to LADWP’s meter spot request page, a representative visits within 5 to 15 business days. The LADBS inspector may ask to see that sketch before approving the panel, and larger panels need an extra service-planning form.
Power gets turned on last. LADWP’s Guide to Electric Service explains that it energizes service after it receives final release from LADBS. Build that step into your move-in date or your rental plans.
Other common additions to the ADU permit timeline include Bureau of Engineering permits when sewer or driveway work happens in the public street, Fire Department review for lots in high fire hazard zones, and a coastal development permit for coastal lots. Historic-district review applies in an HPOZ, or Historic Preservation Overlay Zone, which is a neighborhood with rules that protect its historic look. Each of these has its own staff and its own queue.

How long do inspections take after the permit is issued, and how do I track my status?
Construction and inspections usually take longer than the permit itself, and the pace depends on the build and the inspector's schedule. You can check plan check, permit, and inspection status online through the LADBS Check My Project Status tool.
Once the permit is issued, the city inspects the work at set stages. The exact list depends on the project, but a typical ADU follows this order:
- Foundation, before concrete is poured.
- Underfloor or under-slab work, including plumbing below the slab.
- Rough framing, electrical, plumbing, and mechanical, while the walls are still open.
- Insulation, before the walls are closed.
- Drywall, where the city requires it.
- Final inspection, when the unit is complete.
A failed inspection adds time, because work stops until the problem is fixed and checked again. The cure is the same as with plan check: build to the approved plans and have the work fully ready before you schedule the inspector.
After the final sign-off, LADBS releases the job to LADWP, and the utility connects power. Only then is the unit ready to live in or rent. Check My Project Status shows where your permit and inspections stand, and LADWP has its own online tracker for service requests.
When should you call a licensed contractor about your ADU permit?
Call a licensed contractor before the plans are final, not after the first correction sheet arrives. That matters most if you’re converting an older garage, building on a slope, working in a fire, coastal, or historic zone, or unsure whether your electrical service and sewer line can handle a second unit. A contractor who has opened up plenty of old Los Angeles garages can spot foundation and framing problems that would otherwise show up in plan check or during an inspection.
It’s also worth a call if your plans came back denied and the comments look structural. Villa Bella Construction’s approach is to find the real condition first, then recommend the safest targeted fix the city will accept, so you’re not tearing out more than the problem requires. The building department still decides approvals and timing, but a complete, honest plan set gives your project the best chance of moving steadily.
“The work was very well done and exceeded all my expectations.” — Cindy W., Yelp review
Villa Bella Construction is a licensed and insured general contractor, building in Los Angeles for 25 years. CSLB License #1093648 (B – General Building).
Call +1 (323) 825-9798 or send us your project details.
Learn more: ADUs and garage conversions.
Planning a construction or remodeling project in Los Angeles?
Schedule a Free On-Site Consultation or call +1 (323) 825-9798.