Key Takeaways
- A foundation inspection checklist covers two things: finding what's really wrong with an existing foundation, and passing the city's required inspections on new work.
- Footings, steel and forms must be inspected and accepted before concrete covers them, and some jobs also need a licensed deputy inspector the owner hires.
- Expansive clay, hillsides and older raised foundations change what goes on the list, so a licensed engineer and contractor should set it for your property.
A foundation inspection checklist matters because it keeps two jobs on track. The first is finding what’s really wrong with an existing foundation before anyone spends money on a repair. The second is making sure new footings, slabs and walls pass the city’s required inspections before concrete covers them. Most pages blur these together, and that confusion is how homeowners end up with repairs that miss the cause or work the city won’t sign off. This guide separates them, explains what the city expects, and shows how Los Angeles soils change the list.
What does a foundation inspection checklist actually cover?
The term means two different things. One is a condition check of an existing foundation to find cracks, movement and water problems. The other is the set of required city inspections on permitted foundation work, such as the footing inspection before concrete is poured.
A condition check looks at what’s already there. Someone walks the outside of the house, looks in the crawl space, checks floors for slope and doors for binding, and traces where rainwater goes. The goal is to learn why the foundation is moving or cracking, not just to patch the symptom.
Required city inspections apply once you have a permit for new work or a repair. A city inspector, and sometimes a separate deputy inspector, checks that the work matches the approved plans at set stages. The building department decides those stages, not you.
One doesn’t replace the other. A good condition check tells the engineer and contractor what to design, and the city inspections confirm it was built that way. In older Los Angeles homes, the visible crack is often only the end of the story. The real cause is a downspout dumping water against the stem wall, which is the short concrete wall that holds up the house, or a planter that keeps the soil soaked.
Which foundation and wall jobs need a permit and city inspections?
New footings, foundation repair, underpinning, most retaining walls and many block walls need a building permit. Each permit comes with the inspections the city sets for that job. Only your local building department decides what applies to your property.
Underpinning means extending or strengthening a foundation down to firmer soil, and it almost always needs engineering and a permit. So do new footings for an addition or ADU and replacing a damaged stem wall. Retaining walls and taller or loaded block walls usually need permits too. A slab repair may or may not, depending on what’s under it and what it supports.
First, confirm which building department you’re under. The Los Angeles Department of Building and Safety (LADBS) covers only the City of Los Angeles. Unincorporated county areas and surrounding cities each have their own building departments and inspection systems. A Los Angeles mailing address doesn’t always mean you’re inside city limits, so check the city’s ZIMAS parcel map or call the department.
A permit might need one inspection or a long series, depending on the job. Our page on foundation repair, retaining walls and concrete work explains the kinds of jobs that typically fall under these permits.
What does the city inspector check before concrete is poured?
The inspector checks the excavation, the steel reinforcement and the forms against the approved plans before any concrete goes in. Once concrete covers that work, no one can see it. That's why the city requires the inspection first.
LADBS states on its inspection services page that you must call for an inspection before covering or hiding any work, and that construction isn’t approved until the department has inspected and accepted it. Pouring before that sign-off is one of the costliest mistakes on a foundation job.
The exact order comes from your permit and approved plans. A typical foundation job moves like this:
- The crew digs the footing trenches to the depth and width shown on the plans.
- Rebar, anchor bolts, hold-downs and embedded items are set and tied. Rebar is the steel bar that gives concrete its strength.
- Forms are built, and loose soil and standing water are cleaned out.
- The inspector, and the deputy inspector if one is required, checks the work and signs the inspection card.
- Concrete is poured only after that approval.
- Later inspections follow for framing, walls and final approval, as the permit requires.
Steel size, spacing and coverage come from the engineer’s plans and the code, not a checklist downloaded from the internet. If concrete went in early, the city may require the work to be exposed or tested. That’s why a careful foundation inspection checklist on the job site lists every hold point before the concrete truck is ordered.

When do I need a deputy inspector, and who hires one?
A deputy inspector is a private, city-licensed inspector who watches certain work continuously, such as some reinforced concrete, structural masonry and hillside grading. The owner, or the design professional acting for the owner, must hire them. Whether you need one depends on the scope of work and the approved plans.
Not every foundation or slab job needs a deputy. The city inspector makes stage visits, while a deputy stays on site during specific work, like a structural concrete pour or retaining wall masonry. LADBS explains the role in its information bulletin titled Employment and Duties of a Registered Deputy Inspector.
Your plans list any required special inspections, usually on the structural sheets. Read that list before work starts, then confirm the deputy holds the right certification for each type of work. LADBS warns that if a deputy without the proper certification is used, the city may not approve the related work.
Deputy inspections have their own notice process with the city, separate from booking a regular inspection. Ask who’s responsible so it doesn’t fall through the cracks. A missed deputy inspection can mean testing, exposing work, or an engineer’s letter before the city will move forward.
How do I schedule an LADBS inspection for foundation work?
In the City of Los Angeles, you can request inspections online or through the department's automated phone system. You'll need the permit number, the site address and the type of inspection. LADBS sets the cutoff times and decides when an inspector comes, so plan the pour around their schedule.
Most owners let the contractor book inspections, but it helps to know the usual sequence:
- Have the permit number, job address and inspection type ready, such as footing or foundation.
- Request the inspection online or by the automated phone line. Check the current cutoff time with LADBS, because their own pages have listed different times.
- Make sure the approved plans and permit card are on site and the work area is safe to reach.
- If a deputy inspection is required, confirm the separate deputy notice was sent.
- Don’t order concrete until the inspection is signed off. Reschedule or cancel through the same system if the crew isn’t ready.
Inspector availability changes with workload, weather and holidays, so build some slack into the schedule instead of booking the pump truck for the same morning.
When the job ends, keep the signed inspection card, deputy reports, engineer letters, soils reports and final approval. These papers matter when you sell, when an insurance adjuster asks about past repairs, and after an earthquake. Store copies in two places.
Is a contractor's free foundation inspection enough, or do I need an engineer?
A contractor's walk-through can point out problems, but it doesn't replace a city inspection or a licensed engineer's evaluation. If the foundation is moving, the house sits on a slope, or a repair needs a permit, bring in a structural engineer, and often a geotechnical engineer.
A structural engineer designs how the foundation carries the house. A geotechnical engineer, also called a soils engineer, studies the ground under it and how it behaves when wet, dry or shaking. On hillside and settlement jobs, the soils report often drives the whole design, and in the City of Los Angeles, LADBS reviews those reports during plan review.
Be careful with free inspections that end in a fixed repair package. When the person diagnosing the problem also sells one repair method, you may get that method whether it fits or not. Our approach is to find the real cause first, then recommend the safest targeted repair the city will accept, without tearing out more than the problem requires.
Check licenses before anyone works on your foundation. Look up contractors on the Contractors State License Board site at cslb.ca.gov, and engineers through the Board for Professional Engineers, Land Surveyors, and Geologists at bpelsg.ca.gov. It takes five minutes.
How do clay soils, hillsides and foundation type change the checklist?
Expansive clay swells when wet and shrinks when dry, so the checklist puts drainage and soil moisture near the top. Hillside lots add slope, retaining walls and deep foundations to the list. Slabs, raised foundations and walls each get checked in different places.
Much of the Los Angeles basin has clay that moves with the seasons. After a wet winter you’ll see new cracks and sticking doors, and some of it eases by late summer. So a good foundation inspection checklist asks where roof water lands, whether planters sit against the house, and whether the yard slopes toward the foundation. Our guide on planning hillside foundation drainage goes deeper.
What gets checked depends on the foundation type:
- Slab on grade: cracks and lifting at slab edges, floor slope, plumbing leaks under the slab, and moisture coming up through flooring.
- Raised foundation: stem wall cracks, damp or rotted sill plates (the wood board resting on the concrete), anchor bolts, and cripple walls, the short wood walls between the foundation and the first floor.
- Hillside piles and grade beams: signs of downhill movement, exposed piles, and uphill drainage. Our post on caissons versus grade beams explains these systems.
- Retaining and block walls: leaning, bulging, blocked weep holes, and water behind the wall.
Older raised houses often aren’t bolted or braced. FEMA notes that homes with weak anchoring and flexible cripple walls can slide off their foundations in an earthquake. The California Earthquake Authority runs the Earthquake Brace + Bolt grant program, but eligibility and dates change each round, so check its official site before counting on it.

Which warning signs mean I should get a professional foundation evaluation?
Get an evaluation if cracks are growing, stair-stepping or offset, if floors slope noticeably, or if doors and windows suddenly bind. Water in the crawl space or along slab edges also counts. No single crack width tells the whole story, so look at the pattern and whether it's changing.
Hairline cracks in concrete and stucco are common, and many are just shrinkage. The ones that deserve attention are wider at one end, run diagonally from door and window corners, or show one side higher than the other. Horizontal cracks in a stem wall or retaining wall can mean soil is pushing on it.
Inside, watch for doors that start rubbing, gaps at the tops of door frames, and drywall cracks that return after patching. Outside, look for a porch pulling away, a separating chimney, or a leaning retaining wall. Our article on signs of foundation settlement covers these in detail.
Track changes before you call. Mark crack ends with a pencil and the date, and photograph them from the same spot every few weeks. Movement over time tells an engineer far more than a single snapshot. Add those notes to your own foundation inspection checklist so nothing gets forgotten.
Do I have to call 811 before digging footings or a retaining wall?
Yes. California law requires you to contact DigAlert, by calling 811 or going online, at least two working days before you dig, not counting the day you call. The service is free.
Footing trenches, retaining wall excavations and driveway removal all count as digging. DigAlert’s safe digging guidance lists new foundation excavation as a typical example. You mark the area in white paint first, then submit the ticket.
Utilities mark only the lines they own, usually up to the meter. Private lines like a sewer lateral, a gas line to a back house, or wiring to a garage aren’t marked. On older Los Angeles lots, those lines often run right where a new footing is planned, so locate them separately.
Contractors need their own ticket and can’t dig before the waiting period ends. If anyone hits a line, report it to the utility right away, even if nothing looks damaged.
When should you call a licensed contractor about your foundation?
Call a licensed contractor when cracks keep growing, doors keep binding, or a retaining wall is leaning. Call too if you’re planning footings, underpinning or a new wall that needs a permit. A good contractor works with your engineers, builds to the approved plans, and manages the inspection hold points so nothing gets covered too early. Villa Bella Construction is a licensed and insured general contractor that handles foundation repair, slabs, retaining walls and block walls. We find the real cause first, then recommend the safest targeted repair the city will accept. The building department still decides approvals and timing, and we plan the work around that.
Villa Bella Construction is a licensed and insured general contractor, building in Los Angeles for 25 years. CSLB License #1093648 (B – General Building).
Call +1 (323) 825-9798 or send us your project details.
Learn more: Retaining walls, block walls, concrete slabs, driveways, foundation repair.
Planning a construction or remodeling project in Los Angeles?
Schedule a Free On-Site Consultation or call +1 (323) 825-9798.