Key Takeaways
- Most engineers tie a new addition to the old footing with steel dowels set in epoxy, but some designs keep the addition separate with a planned joint.
- The engineer of record decides how the two connect, and the city building department reviews the plans and inspects the steel before concrete is poured.
- Soil, footing depth, the old foundation's condition, and drainage at the seam decide whether the two parts settle evenly or crack apart.
Most engineers tie addition to existing foundation footings with steel dowels. Dowels are short rebar pins drilled into the old concrete, set in epoxy, and wired to the new rebar before the pour. A footing is the concrete strip in the ground that carries the weight of your walls. Some designs do the opposite and put the addition on its own foundation, with a planned joint between old and new. Either way, a California-licensed engineer or architect decides how the connection works, and your city building department approves the plans and inspects the steel before any concrete goes in.
Do you always tie addition to existing foundation footings, or can it stand alone?
Not always. Many single-story additions are doweled into the old footing so the house and the new room move together. Larger or heavier additions, or additions on different soil, are sometimes built on their own foundation with a separation joint.
The connection matters most in an earthquake. California designs buildings for lateral loads, which means the sideways push a quake puts on a house. If the new room and the old house are tied together, they sway as one unit, so the engineer plans the steel, anchor bolts, and wall bracing to carry that push across the seam.
The other option is a separation joint. That’s a planned gap with a flexible filler that lets each part move on its own. Engineers choose it when the soil under the addition behaves differently, when the addition is much heavier than the house, or when the old foundation can’t safely take new steel. It isn’t a shortcut. Each side then has to stand up to an earthquake by itself.
Online forums are full of people who swear one method is always right. Engineers honestly disagree, and the right answer depends on your lot. In the City of Los Angeles, LADBS reviews the foundation plan during plan check and may ask for changes. The building department decides when the design is approved, not the contractor.
How are dowels set into my existing footing?
The crew exposes the side of the old footing, drills holes, cleans them, and sets short steel bars in structural epoxy. Those bars are tied to the new rebar so the fresh concrete locks around them. The engineer's drawings set the size, spacing, and depth of every dowel.
Epoxy here is a two-part structural adhesive made to grip steel inside concrete. It anchors each dowel. It doesn’t glue the whole face of the new concrete to the old. The steel does the tying.
Done right, the work follows a clear order:
- Have underground utilities marked before anyone digs.
- Dig along the old footing, by hand near the house, so you can see what’s there.
- Check the old concrete. If it crumbles, has no rebar, or isn’t where the plans assumed, stop and call the engineer.
- Drill holes at the depth and spacing on the plans, avoiding steel already in the old footing.
- Blow and brush every hole clean. Dust left inside weakens the grip.
- Inject the epoxy, set the dowels, and let them cure as the product instructions require.
- Tie the dowels to the new rebar, then set forms, anchor bolts, and hold-down hardware.
- Call for the city foundation inspection, and pour only after the inspector signs off.
Some plans also call for a special inspector to watch the anchors go in. That visit has to happen before the pour, so build it into the schedule from the start.
Will the addition settle differently from my house and crack where they meet?
It can, and that's the main reason the connection gets so much attention. Your house has sat on the same soil for decades, while the new footing sits on freshly dug ground that has never carried weight. Good soil preparation, the right footing design, and a planned connection keep that difference small.
Engineers call this differential settlement. It simply means one part of a building sinks a little more than the part next to it. Soil under your house has already squeezed down as far as it’s going to. New soil hasn’t, especially if it was loosened during digging or brought in as fill.
In older Los Angeles neighborhoods with clay soil, the ground swells in wet winters and shrinks in dry summers. A new footing can move on a slightly different rhythm than an old one. That’s why a crack sometimes shows up right where the old wall meets the new one, a season or two later. Diagonal drywall cracks at that corner or a sticking door into the addition look a lot like the general signs of foundation settlement, and they deserve the same early look.
When a soils report is required, LADBS expects it to deal with this directly. The city’s guidelines for soils and geology reports say the report should address estimated differential settlement between an existing structure and a proposed addition. That estimate shapes how the engineer draws the steel and the joint.

Do I need a structural engineer and a soils report for my lot?
For an addition tied into your foundation, plan on a structural engineer or architect preparing the foundation plan and calculations. Whether you also need a soils or geology report depends on your lot, including slopes, hillside areas, fault zones, seismic hazard zones, and digging that removes support from nearby soil.
The LADBS homeowner’s guide to permits and inspections lists a foundation plan among the drawings you submit, and says engineered work needs the original drawings and calculations from your engineer or architect. Connecting new foundation to old is almost always engineered work.
The soils question depends on the ground. The LADBS answers on soils reports list triggers such as a slope steeper than 3 to 1, digging that removes lateral support, fault rupture zones, Hillside Grading Areas, and seismic hazard zones. You can look up your parcel in ZIMAS, the city’s online parcel map, to see which zones apply. Before hiring, check the contractor’s license with the Contractors State License Board and the engineer’s or geologist’s with the state Board for Professional Engineers, Land Surveyors, and Geologists.
Not every part of an addition needs a custom design. On one small home addition, Villa Bella Construction prepared the drawings and had the engineer use the city’s standard-plan wood framing instead of a full custom redesign with a long round of custom calculations. A plan checker pushed back. We brought it to a senior person at the building department, showed the framing followed the city’s own standard path, and the plans were ordered passed. The standard-plan path shortened that dispute and saved the owner time and extra plan and engineering cost. We could have sold the longer custom route, and we didn’t.
How deep do the new footings have to go compared to my existing ones?
Deep enough to reach soil that can carry the load, which may be deeper than your old footing. The depth comes from the building code and, when there is one, the soils report. Matching the old footing's depth isn't the rule.
Much of the advice online comes from cold places where footings go below the frost line, the depth where the ground freezes. That isn’t a concern on most Los Angeles lots. What matters here is reaching firm, undisturbed soil at the depth the code and the engineer require.
Older Los Angeles houses often sit on shallow footings poured long before current codes, so a new footing may need to go deeper. Digging a deep trench right beside a shallow footing can pull soil out from under it. The engineer may step the new footing down gradually or require the work in short sections. On hillside lots, the addition may stand on caissons, deep concrete piers drilled to firm soil or rock, linked by grade beams. Our guide to caisson versus grade beam foundations explains those choices.
Sometimes the trench turns up loose fill, an old buried footing, or soft clay. The city can require a soils or geology report at that point, and the building department decides what has to happen before work continues.
What if my existing foundation is old, cracked, or made of brick?
Then it may not be able to hold a dowel, and the engineer will need a different plan. That can mean strengthening or underpinning the old footing first, or putting the addition on its own foundation with a joint. You want to know this before the design is final, not after the trench is open.
Many early Los Angeles houses sit on brick or unreinforced concrete footings. Unreinforced means there’s no steel inside. You can’t safely tie addition to existing foundation concrete that crumbles when you drill it, because the dowel has nothing solid to grip.
The weakest stretch of footing is often at the back of the house, where downspouts and sprinklers have dumped water for years. That’s usually where an addition goes. If the old footing is weak, the fix may be underpinning, which means adding new concrete beneath or beside it so it rests on firmer support. That’s real foundation repair and concrete work, best handled under the same permit and design.
Watch for unpermitted earlier work, too. If a past owner added a room without permits, the city may require that part to be legalized or corrected before your new work moves forward. Either surprise can mean revised drawings, and the building department sets the review timeline for those changes.

How is a raised wood-floor house tied to a new slab addition?
The engineer has to bring two different systems together at the wall line. That might mean a new perimeter footing and stem wall that lift the addition floor to match the old floor, or a slab set lower with a step between rooms. The plans show how the new framing bolts and braces to the old framing as well as to the old footing.
A raised wood floor sits above a crawlspace, with a perimeter footing around the edge and posts and piers inside. A slab house sits directly on concrete at ground level. A stem wall is a short concrete wall rising from the footing to support floor framing. On older raised houses, a cripple wall, a short wood wall between foundation and floor, often sits on top and needs earthquake bracing and bolting where the addition meets it.
Don’t block the crawlspace vents. An addition across the back of the house can cover the openings that let the crawlspace breathe, and moisture builds up under the floor. The plans should keep or replace that ventilation and leave a way in.
You’ll also cut an opening in the old exterior wall to join the rooms. That wall usually carries the roof above, so read up on planning structural wall openings before deciding how wide to go.
Will digging next to my house undermine it, and who calls 811?
Careful digging shouldn't, but a trench beside an old footing can let soil slide out from under it if it's dug too deep or left open too long. The contractor doing the digging should contact DigAlert through 811 before breaking ground, and you should ask to see the ticket.
Soil holds up a footing from below and from the sides. Take away the soil on one side and the footing can shift. That’s why digging that removes lateral support can trigger a soils report, and near a property line the same risk applies to your neighbor’s wall or garage. Trenches are dangerous for workers, too. OSHA’s trenching and excavation guidance says trenches 5 feet or deeper need protection such as sloping, benching, shoring, or shielding.
Before any digging, the contractor should request markings through DigAlert’s safe digging program at least two working days ahead. Utilities mark only the lines they own, usually up to the meters. Your private sewer line, sprinkler pipes, and garage power line won’t be marked, so walk the yard with your contractor and point out what you know.
A trench left open through a winter storm can soften and cave. A good crew digs, inspects, and pours without leaving the old footing exposed longer than needed.
How is water kept out where the old and new foundations meet?
The seam between old and new concrete is a weak spot for water, so it needs a planned detail. That usually means ground sloping away from the house, waterproofing or sealant across the joint, and a clear path for water to drain. If the addition blocks an old drainage route, that water has to go somewhere else.
New concrete poured against old leaves a line where water can creep in. On a slab addition, it shows up as damp flooring at the transition. On a raised house, it ends up in the crawlspace.
Additions change how water moves. A new roof adds downspouts, and a new foundation can cut across the path rainwater used to take to the street. If nobody plans for it, water ponds against the seam, the soil softens, and that’s where settlement starts. Keep soil below the bottom of the walls, too. On stucco houses, the weep screed is the metal strip at the base of the stucco that lets trapped water out, and burying it sends water into the framing.
On sloped lots, drainage is part of the foundation design, not an afterthought. Our article on hillside foundation drainage covers the drains and grading that keep water away from footings.
When should I call a licensed contractor about tying an addition into my foundation?
Call before your design is final, not after the trench is open. Bring in a licensed contractor if your house is old, you’ve seen cracks or sticking doors, your lot slopes, or part of the house was added without permits. A small test pit dug early shows the engineer what the old footing really looks like, so the plans fit the house you actually have.
Villa Bella Construction is licensed and insured. We find the real condition of the old foundation first, then recommend the safest targeted connection the city will accept, without tearing out more than the job requires. Your engineer designs it, and the building department approves it.
“If you want an honest, licensed contractor in the LA area, I highly recommend them!” — Robert H., Google review
Villa Bella Construction is a licensed and insured general contractor, building in Los Angeles for 25 years. CSLB License #1093648 (B – General Building).
Planning a construction or remodeling project in Los Angeles?
Schedule a Free On-Site Consultation or call +1 (323) 825-9798.